Posted Fri, 10 Jan 2020 17:22:29 GMT by Michael Weingand Professional Services Manager
DW 7.2
In Workflow, I am trying to calculate a date based on a date field - 45 days.  Does anyone have a solution.  I thought it was as simple as GV_EndDate - 45.  But nope.

Any help would be greatly appreciated.
 
Posted Fri, 10 Jan 2020 18:59:23 GMT by Jon Weston File IT Solutions Sr Application Developer and RIM specialist
Hi Michael,
You'll need to use the DateAdd function.  I have this page bookmarked - it'll tell you about that and all the other functions: VB Scripts
Posted Fri, 10 Jan 2020 23:09:21 GMT by Michael Weingand Professional Services Manager
Thank you so much for the help.  This worked perfectly and easily.